Thanks for your reply.
I have detail:
We consider applied screw conveyor or scraper conveyor for bottom ash handling in Boiler island only.
For plant ash (bed ash and fly ash) handling system, we must convey ash to pond by trucks.
Now this way was being high cost (maintenance and operation cost) so we want to use tube pipe conveyor but
1. We do not understand calculation way
2. The temperature of ash is 150oC, is it Ok for tube's material (Fabric).
Pls. help me? any expert guys?